Roadway reconstruction of Highland Drive between McKinley Woods Road and Leslie Drive is scheduled to begin this Wednesday, April 26, 2023 and continue for six weeks.
Reconstruction consists of the removal and replacement of the existing asphalt, curb and gutter, driveway aprons, road grading, and spot sidewalk ADA improvements.
Questions or concerns may be directed to Public Works at 815-467-6644.